The Meadows - Plots 3 & 4 Build Progress
Available Today - Plot 3 Sold Subject to Contract, Plot 4 Sold April 2024
8th September - Plot 4 Show Home now Ready
10th June 2023 - Plaster Boarding progressing
9th April 2023
18th March 2023
3rd March 2023 - Roof complete, light tunnels installed
Plot 3 1st fix started
9th January 2023
7th November - Progressing 1st floor
14th September 2022
27th August 2022
Plot 3 Rear
Plot 4 Rear
22nd July
15th July
25th June - Plot 3 Ground floor walls started
25th June - Plot 4 awaiting start of blockwork
16th June - waiting for blockwork to start
10th June - ground floor concrete
2nd June - Blockwork to damp proof course completed
28th May - Foundation concrete poured
24th May - Pots 3 & 4 foundations dug out
21st May - Plot 3 & 4 land cleared
4th March - Corner pins marked for plot 4