The Meadows - Plots 3 & 4 Build Progress

Available Today - Plot 3 Sold Subject to Contract, Plot 4 Sold April 2024

8th September - Plot 4 Show Home now Ready

10th June 2023 - Plaster Boarding progressing

PLot 3 Walkthrough

Plot 4 Walkthrough

9th April 2023

18th March 2023

3rd March 2023 - Roof complete, light tunnels installed

Plot 3 1st fix started

9th January 2023

7th November - Progressing 1st floor

14th September 2022

27th August 2022

Plot 3 Rear

Plot 4 Rear

22nd July

15th July

 25th June - Plot 3 Ground floor walls started

 25th June - Plot 4 awaiting start of blockwork

 16th June - waiting for blockwork to start

 10th June - ground floor concrete

 2nd June - Blockwork to damp proof course completed

 28th May - Foundation concrete poured

 24th May - Pots 3 & 4 foundations dug out

 21st May - Plot 3 & 4 land cleared

4th March - Corner pins marked for plot 4

Corner pin for rear of plot 4

Corner pin for front of plot 4