The Meadows - Plot 8 Build Complete
Sold March 2023
31st March 2023 - Completion day - Handing over to new owners
18th March 2023 - Ready for Completion
4th March 2023 - final decoration before snagging can take place
23rd December 2022
25th November
18th November 2022 - Painting started on ground floor
15th August 2022 walkthrough
Plot 8 Rear Garden
7th August 2022 - fully plaster boarded ready for skimming
22nd July
15th July
8th July - Windows are in
25th June 2022 - first fix joinery, electrics and plumbing
11th May - Under Floor heating installed to ground floor and screeded
29th April - Lounge roofs are on, ground floor insulation in ready for underfloor heating and screeding
1st April - Scaffolding removed and stairs installed
25th March - Roof complete, waiting for scaffolding to come down
10th March - Roof tiles progressing
5th March 2022 - Roof tiles and roof windows progressing
25th February - Staircases have arrived
4th February 2022 - Plot 8 1st and 2nd floor battened
28th January 2022
External Progress
20th January 2022
17th January 2022 - Roof going on
7th January 2022 - 2nd floor started
22nd December 2021 - Steels to hold 2nd floor installed
19th December 2021 - Walls to 2nd floor complete
10th December 2021
29th November 2021 - Walls to 1st floor and 1st level flooring in
14th November 2021
6th November 2021
25th October 2021 - Ground floors complete
16th October 2021
8th October 2021 - Foundations are in