The Meadows - Plot 8 Build Complete

Sold March 2023

31st March 2023 - Completion day - Handing over to new owners

18th March 2023 - Ready for Completion

4th March 2023 - final decoration before snagging can take place

23rd December 2022

25th November

18th November 2022 - Painting started on ground floor

15th August 2022 walkthrough

Plot 8 Rear Garden

Plot 8 Rear Garden

7th August 2022 - fully plaster boarded ready for skimming

22nd July

15th July

8th July - Windows are in

 25th June 2022 - first fix joinery, electrics and plumbing

Hallway

Cloak Room & Lounge

Garage

Storage for someone’s extra large sofa??

Utility Room

 11th May - Under Floor heating installed to ground floor and screeded

 29th April - Lounge roofs are on, ground floor insulation in ready for underfloor heating and screeding

 1st April - Scaffolding removed and stairs installed

 25th March - Roof complete, waiting for scaffolding to come down

 10th March - Roof tiles progressing

 5th March 2022 - Roof tiles and roof windows progressing

 25th February - Staircases have arrived

 4th February 2022 - Plot 8 1st and 2nd floor battened

Plot 8 1st floor

Plot 8 - Bedroom 2 Ensuite

Plot 8 Bedroom 2 Ensuite

Plot 8 Bedroom 5

Plot 8 Principal Bedroom

Plot 8 2nd Bedroom

Plot 8 Bedroom 3

Plot 8 Family Bathroom

Plot 8 -Bedroom 4

Plot 8 Principal Bedroom Dressing and Shower Rooms

 28th January 2022


External Progress

 20th January 2022

 17th January 2022 - Roof going on

 7th January 2022 - 2nd floor started

 22nd December 2021 - Steels to hold 2nd floor installed

 19th December 2021 - Walls to 2nd floor complete

 10th December 2021

Plot 9 - Dining and Lounge patio door spaees

Plot 9 - View from front door - kitchen to right, dining area far right, lounge in far front

 29th November 2021 - Walls to 1st floor and 1st level flooring in

 14th November 2021

 6th November 2021

 25th October 2021 - Ground floors complete

 16th October 2021

 8th October 2021 - Foundations are in