The Meadows - Plot 5 Build Progress - Sold

January 2022

24th February 2023 - Turf laid and home complete for handover

17th February 2023

9th January 2023

16th December

25th November

18th November

11th November - Top Floor plastering started

7th November - Plaster boarding in progress

4th November

28th October

17th October 2022

14th October 2022

7th October

Top Floor first fix joinery and plumbing

Top Floor 1st fix Joinery and plumbing

1st Floor 1st fix joinery and plumbing

14th September 2022

27th August 2022

20th August 2022

17th August 2022

15th August 2022

7th August - Gable walls progressing

22nd July

15th July

8th July

 25th June 2022 - scaffolding moved for 2nd half of 1st floor walls

 16th June 2022 - 1st floor walls progressing

 10th June 2022 - 1st floor joists going in

 28th May - Walls complete to 1st floor ready for 1st floor next week

 24th May - Ground Floor walls progressing

 21st May - Ground floor walls progressing

 13th May - Scaffolding up and walls progressing to 1st floor

 6th May - Ground Floor walls progressing

 29th April

 27th April

 22nd April - Ground floor walls starts

 4th March - Complete to Ground floor and base concrete poured

 12th February - Foundations poured

 4th February 2022 - Foundations started to be dug