The Meadows - Plot 5 Build Progress - Sold
January 2022
24th February 2023 - Turf laid and home complete for handover
17th February 2023
9th January 2023
16th December
25th November
18th November
11th November - Top Floor plastering started
7th November - Plaster boarding in progress
4th November
28th October
17th October 2022
14th October 2022
7th October
Top Floor 1st fix Joinery and plumbing
1st Floor 1st fix joinery and plumbing
14th September 2022
27th August 2022
20th August 2022
17th August 2022
15th August 2022
7th August - Gable walls progressing
22nd July
15th July
8th July
25th June 2022 - scaffolding moved for 2nd half of 1st floor walls
16th June 2022 - 1st floor walls progressing
10th June 2022 - 1st floor joists going in
28th May - Walls complete to 1st floor ready for 1st floor next week
24th May - Ground Floor walls progressing
21st May - Ground floor walls progressing
13th May - Scaffolding up and walls progressing to 1st floor
6th May - Ground Floor walls progressing
29th April
27th April
22nd April - Ground floor walls starts
4th March - Complete to Ground floor and base concrete poured
12th February - Foundations poured
4th February 2022 - Foundations started to be dug