The Meadows - Plots 1 Build Progress
Available from Autumn 2023
3rd November 2023 - Almost finished
8th June - Plastering almost Complete
23rd June - Underfloor heating in and screeded
22nd May - Roof is on
12th May 2023 - Roof going on
9th April 2023
3rd March 2023 - Work Resumed with new builders
9th January 2023
7th November
14th September
27th August 2022
7th August - Ground floor walls 2/3rd complete and floor concrete poured - ready for scaffolding
22nd July - waiting for external walls and Ground Floor concrete
15th July - walls to DPM and ground floor going up
8th July - Foundations poured