The Meadows - Groundworks Progress

September 2021 to September 2023

14th September - Plots 8 & 9 connections being established

20th August 2022 - Curb and utilities trench

27th August - Utilities getting installed

 21st May - last manhole complete

 13th May - Final manhole ready for concrete base pour on Monday

 4th May - Entrance Road tarmacked

 29th April - Road being prepared for tarmack and neighbours garage drives concreted

 8th April - Drainage pipes laid, last manhole to install and road curbs have started

 1st April - Drainage extending into site and 1st road drain ready

 29th March - Drainage continues

 25th March - More Drainage holes …

 10th March - Drainage in Entrance Road started and Retaining wall next o Neighbours land progressing

 4th March - Drainage progressing and Plot 4 side retaining wall

Drain at intersection with hammerhead installed

Main drains from hammerhead complete

Retaining wall at side of plot 4 foundations

 25th February - Hammerhead drain and west drains in ready for intersection manhole to be installed

 18th February - Wet and Muddy - not safe to continue once boots got left behind in the mud

 12th February - Drainage and Plot 5 foundations continue

 4th February 2022 - Drainage started and foundations for plot 5 being prepared

 27th January 2022 - Groundworks preparation for plots 3, 4 and 5

Road leading to site

View of Plots 1 to 4 from Plot 9 top side window

Plot 5 base prepared ready for foundations to be dug